PRO TIP when you face a Business Conflict

Collaborate, Don't Confront: In ADR, success lies in collaboration, not confrontation. Embrace open communication, actively listen, and work together towards a solution that benefits all parties involved.

Private Court Symbol
The International Court of ARBITRATION

News

Orissa High Court Rejects Arbitration Plea in Power Project Dispute

28 March 2025
Orissa High Court Rejects Arbitration Plea in Power Project Dispute
In a significant legal development, the High Court of Orissa has dismissed an arbitration petition filed by Andhavarapu Power Projects Private Limited against the Odisha Renewable Development Agency (ORDA), highlighting critical nuances in dispute resolution mechanisms.

The case, ARBP No.61 of 2023, centered on a long-standing agreement dated January 22, 2010, where the power project company sought arbitrator appointment after allegedly receiving no response to its commencement notice issued on July 25, 2023.

Key Legal Insights

The core of the dispute revolved around Clause 19 of the original agreement, which stipulated that "any dispute regarding any clause in this agreement" should be referred to the Orissa Electricity Regulatory Commission (OERC), with OERC's decision binding on both parties.

Acting Chief Justice Arindam Sinha meticulously examined the case, ultimately concluding that no genuine arbitration agreement existed. He referenced a crucial legal provision, sub-section (6-A) of Section 11 of the Arbitration and Conciliation Act, 1996, which mandates courts to exclusively examine the existence of an arbitration agreement.

OERC's Decisive Intervention

Mr. Bijay Kumar Dash, representing ORDA, highlighted that OERC had already addressed the dispute through an order dated June 3, 2023. The regulatory body refused to entertain the reference, directing the parties to approach an appropriate forum.

Justice Sinha concurred, stating, "It is clear from the reproduced clause 19 in the agreement that reference was to be to OERC. The authority considered the question of reference and concluded that the statute does not permit it to enter into the reference."

Implications and Future Recourse

Notably, the court's judgment provides a silver lining for Andhavarapu Power Projects. The dismissal order explicitly states that the rejection "will not prevent applicant from finding remedy in law including seeking exclusion of time taken."

Legal Precedent

The court referenced a previous judgment from August 11, 2017 (ARBP no.19 of 2016) involving Enzen Global Solutions, which had different communication dynamics allowing arbitration. However, the current case was distinguished based on its specific contractual nuances.

Legal experts suggest this judgment underscores the importance of precise dispute resolution clauses in infrastructure and power project agreements, emphasizing the need for clear arbitration mechanisms.

Read The Judgment Here

Arrow

keywords: Orissa High Court, Power Project Dispute, Arbitration Petition, OERC Intervention, Contract Dispute, Renewable Energy Agreement.

Got any
Questions

Write to us

legal@privatecourt.in

Share this page